SCOTTSDALE, AZ - FASHION SQUARE MALL - KITCHELL

The Tri City Mechanical team with nearly 40 workers on the job accomplished some fancy footwork when it came to timing. The mission critical project was to include a temporary cooling system on Thanksgiving day while the mall was closed, a tricky proposition considering work was being done in a functioning mall. The mall had to be up and running the following day - Black Friday. The biggest shopping day of the year.
Tri City started the demolition on the Wednesday night before Thanksgiving day. The project was mapped out hour by hour in 15-minutes segments. The 30-hour temporary chiller tower project was on-line by 4am on Black Friday morning ready for shoppers.
At Tri City we employ state-of-the-art technology and software including:
- Autocad 2010 MEP for 3D modeling
- CADDuct /CADMech 2010 add-on for HVAC, piping, and plumbing systems
- Autodesk Navisworks 2010 or for interoperability/clash testing
- Revit MEP 2010 as an enhanced alternative to Navisworks